₹37.49 Cr Equity and 91.49% IRR: Why a Maharashtra Steel Board Still Said “No” to a 120 MWp Solar Pitch

Executive Summary

A Maharashtra-based steel manufacturer was presented with a 120 MWp Open Access Solar project under a Group Captive structure. The paper returns were staggering: a 91.49% IRR on equity and ₹2.89/unit in direct savings. Yet, when the CFO asked for a ₹37.49 Cr equity investment, the Board refused to approve it.

They didn’t reject the project; they rejected the lack of forensic transparency regarding the ₹480.7 Cr Total Project Cost. By intervening and building a “Board-Ready Cost Anatomy” framework, we decoded every rupee, percentage, and hidden component. The result? The CFO returned to the boardroom with absolute clarity, securing unanimous approval for the capital expenditure. Here is the exact breakdown of how we did it.

The Pitch: A “No-Brainer” on Paper

When a CFO walks into a boardroom to pitch a Renewable Energy transition, the initial focus is almost always on the top-line financial metrics. For this specific steel company, the numbers for the proposed 120 MWp Open Access Solar project were incredibly compelling:

The Board was happy with the projected savings. They liked the massive 91.49% internal rate of return. For a capital-intensive industry, securing cheap, green power is a strategic imperative.

But they didn’t approve the investment. Not yet.

The Reality Check: The Board’s Sharp Mandate

A high-level spreadsheet is never enough to justify a ₹480.7 Crore capital decision. The Board drew a line in the sand and demanded complete, forensic transparency.

They asked a series of very sharp, specific questions:

The Board made their stance absolute: “Until we get answers to these questions, we will not approve this investment.”

The Forensic Anatomy: Decoding the ₹480.7 Cr

The CFO took on this challenge and reached out to us. He needed to decode the Board’s exact questions and return with a framework that left zero blind spots.

We built the exact “Cost Anatomy” table for him. We mapped every component, separated the hard assets from the soft liabilities, detailed the exact taxation impact, and clarified the debt-to-equity ratio.

(Note: The numbers in the final table should be illustrative but boardroom-accurate to protect confidentiality).

The Verdict: Total Transparency Equals Unanimous Approval

He took this framework back to the Board. This time, they saw the full picture—every component, every percentage, every single rupee accounted for.

Because the financial risk was entirely demystified, the Board approved the ₹37.49 Cr equity investment unanimously.

When the Board asks, “Where exactly does the ₹480 Cr go?”, you must have the answer ready. Not after the meeting. Before it.

Next Steps for the Boardroom

If you are preparing your next Board presentation for an Open Access Solar project, do not rely on a basic developer proposal. You need a ready reckoner to decode your total project cost.

If you want to know how project costs change when you scale from 120 MWp to 300 MWp or 500 MWp, and how economies of scale actually come into play, we can help.

Get a buy-side read on your PPA

Send us the PPA, tariff sheet, or EPC quote you are about to sign. We will stress-test the numbers from the buy-side and tell you where the risk actually sits — before you sign, not after.

Send us your PPA to stress-test

About Infinia Solar

Infinia Solar is India’s leading buy-side renewable-energy advisory. We help large Commercial & Industrial buyers procure the right renewable energy — from the right developers, on the right PPA terms — representing the buyer, never the developer.

We’ve advised 65+ corporates across 19 states, enabling 1.6 GW of solar, wind and hybrid capacity and ₹6,500 Cr of projects across 150+ PPAs with 40+ developers — and zero portfolio defaults.

Talk to Gaurav on WhatsApp