Decode · Open Access · Bihar

Bihar Open Access Solar: ₹6.25 Grid vs ₹4.00 Landed. How a Steel CFO Unlocked ₹2.25/Unit.

Few developers could say whether Bihar delivers ₹2 a unit. The charge stack, read line by line, said ₹2.25.

Executive Summary

A steel plant in Bihar was consuming around 7.5 Crore units a year at ₹6.25 a unit, after the grid subsidy: an electricity bill close to ₹47 Crore. Few developers could tell the CFO whether Bihar could save more than ₹2 a unit. Decoding the Open Access charge stack line by line showed a ₹3.85 busbar Solar PPA landing at ₹4.00 a unit at the plant: ₹2.25 a unit below the grid, ₹13.95 Crore of Year-1 savings on ₹17.0 Crore of equity, and the equity back in 14.7 months.

The Mandate: Cost Pressure and Revenue Pressure

For a steel plant, power is not an overhead line. It is a raw material, and its price sits inside the cost of every tonne shipped.

The Board gave the CFO three conditions, and all three had to hold at once:

At around 7.5 Crore units a year on a 17 MVA contract demand, the bill was close to ₹47 Crore. This was not only cost pressure. It was revenue pressure.

The Illusion: “Bihar Cannot Deliver”

The CFO put one question to the market: can Bihar actually deliver savings of more than ₹2 a unit?

The market in the state is small, and few developers could answer. Bihar was treated as unmapped: a market without enough precedent to model. That word does a lot of work. It is not a calculation. It is the absence of one.

The Reality Check: Four Questions Before the Board

The CFO knew that when he presented to the Board, he had to answer four precise questions:

  1. The landed tariff: what can the plant expect to pay per unit in Bihar?
  2. The busbar tariff: what does the Solar PPA cost at injection?
  3. The Open Access charges: which charges apply, and which do not?
  4. Savings, return and payback: how much does the plant save, how much equity goes in, and when does it come back?

The Forensic Audit: From Injection to Plant

The quoted tariff is the price at the point of injection. What matters to a CFO is the price at the meter, after every charge and loss the state applies.

LineFigureWhat it is
Grid tariff₹6.25 / unitWhat the plant was paying, after the grid subsidy
Solar PPA, busbar₹3.85 / unitThe tariff at injection
SLDC fee₹0.01 / unitThe only charge Bihar does not waive
Wheeling loss in kind (3.36%)₹0.14 / unitEnergy lost in transit
Landed tariff₹4.00 / unitAt the plant
Saving per unit₹2.25 / unitOn 90.7% of the load replaced
Year-1 savings₹13.95 CroreNet, in the first year
Group Captive equity₹17.0 CroreThe consumer's equity stake
Equity payback14.7 monthsThe decision number

The whole argument sits between ₹3.85 and ₹4.00. Bihar waives transmission charges, wheeling charges, cross-subsidy surcharge and additional surcharge for Open Access. What remains is a ₹0.01 SLDC fee and a 3.36% wheeling loss in kind. That is a fact about the state's rulebook, not about a developer's optimism, and it is exactly what “unmapped” had hidden.

The Verdict: The Board Approved

The CFO took this to the Board. The Board saw ₹2.25 a unit of savings and approved the proposal: not because solar was virtuous, but because the landed number cleared the ₹2 mandate, and the equity came back in 14.7 months.

Next Steps for the Boardroom

The same four questions work for any state, not only Bihar. Before accepting that a state cannot deliver, decode the complete charge stack line by line:

Frequently Asked Questions

Can Open Access Solar deliver more than ₹2 per unit of savings in Bihar?

In this case, yes. Against a grid tariff of ₹6.25 a unit, a ₹3.85 busbar Solar PPA landed at ₹4.00 a unit at the plant under a Group Captive structure: a saving of ₹2.25 a unit. The figure depends on the charges that apply to your structure and must be re-run at the time of signing.

What is the difference between a busbar tariff and a landed tariff?

The busbar tariff is the price at the point of injection into the grid. The landed tariff is what the consumer pays at the plant after wheeling charges, losses and applicable levies. In this Bihar case, a ₹0.01 SLDC fee and a 3.36% wheeling loss in kind (₹0.14) took ₹3.85 at the busbar to ₹4.00 landed.

Why did Open Access charges add so little in Bihar?

Because Bihar waives transmission charges, wheeling charges, cross-subsidy surcharge and additional surcharge for Open Access. What remains is a ₹0.01 SLDC fee and the 3.36% wheeling loss in kind. Other states charge what Bihar waives, so the same busbar tariff lands higher elsewhere.

How much equity does a Group Captive solar project require?

In this case ₹17.0 Crore, against Year-1 savings of ₹13.95 Crore, with the equity back in 14.7 months. Group Captive requires the consumer to hold a qualifying equity stake, so the figure scales with plant size.

What does it mean when a state is called unmapped?

It usually means there is limited local precedent to model from, not that the economics fail. It is the absence of a calculation rather than the result of one.

Sources

  1. Gaurav Kawatra, LinkedIn post, 17 September 2026. www.linkedin.com
  2. Infinia Solar, "Bihar Open Access Solar" (video), YouTube, 17 September 2026. www.youtube.com

Get a PPA read before you sign

Send us the PPA, tariff sheet or proposal you are about to sign. We’ll show you where the 25-year risk sits — before you sign.

Send us your PPA to stress-test

About Infinia Solar

Infinia Solar is India’s #1 Corporate & IPP Renewable Energy Advisory. We help large Commercial & Industrial buyers procure the right renewable energy — from the right developers, on the right PPA terms — with every clause decoded before it is signed. We also advise independent power producers on market entry, PPA structuring and exit-ready contracts.

We’ve advised 70+ corporates across 20+ states, enabling 2 GW of solar, wind and hybrid capacity and ₹8,000 Cr+ of projects across 157+ PPAs with 40+ developers — and zero defaults in 7 years.

PPA Guide
The most common solar PPA red flags →
On every mandate, Infinia decodes the commercial terms — we benchmark your tariff and read the clauses line by line.
Talk to Gaurav on WhatsApp